Transport of an 84 t cold box

With 14 Goldhofer axles, the transport from Linde Engineering Tacherting went over 2 days to Passau in Bayernhafen.

Here the cold box was transferred to the barge in a tandem lift with the port crane and a mobile crane.

The journey on the waterways went from there to the Sappi port of Stockstadt am Main. The 84 t were transferred from the barge onto the Greiner 150 t lifting lever tank bridge.

The transport was driven from Darmstadt to the FAIR construction site in one night.